Southend-on-Sea City Council (23 015 785)

Category : Children's care services > Other

Decision : Upheld

Decision date : 06 Mar 2024

The Ombudsman's final decision:

Summary: We will not investigate Mr X’s complaint about children services’ actions. We have upheld Mr X’s complaint as the Council has now agreed to follow the Children Act statutory complaints’ procedure.

The complaint

  1. Mr X, says the Council failed to properly reply to his children services’ complaint.

Back to top

The Ombudsman’s role and powers

  1. We investigate complaints about ‘maladministration’ and ‘service failure’. In this statement, I have used the word fault to refer to these. We provide a free service but must use public money carefully. We may decide not to start or continue with an investigation if we are satisfied with the actions a council has taken or proposes to take. (Local Government Act 1974, section 24A(7), as amended)

Back to top

How I considered this complaint

  1. I considered information provided by Mr X and the Council.
  2. I considered the Ombudsman’s Assessment Code.

Back to top

My assessment

  1. The law sets out a three-stage procedure for councils to follow when looking at complaints about children’s social care services. The accompanying statutory guidance, Getting the Best from Complaints, explains councils’ responsibilities in more detail.
  2. The first stage of the procedure is local resolution. Councils have up to 20 working days to respond.
  3. If a complainant is not happy with a council’s stage one response, they can ask that it is considered at stage two. At this stage of the procedure, councils appoint an investigator and an independent person who is responsible for overseeing the investigation. Councils have up to 13 weeks to complete stage two of the process from the date of request.
  4. If a complainant is unhappy with the outcome of the stage two investigation, they can ask for a stage three review by an independent panel. The Council must hold the panel within 30 days of the date of request, and then issue a final response within 20 days of the panel hearing.
  5. Mr X complained to the Council in July 2023 about children services’ actions. The Council replied at stage one of the Children Act statutory complaints’ procedure in September 2023. Mr X requested this be escalated to stage two in October 2023. The Council says this has still not been completed.
  6. If we were to investigate it is likely we would find fault causing the complainant injustice. The Council has not completed the stage two investigation within the regulation timescale of a maximum of 65 working days.

Back to top

Agreed action

  1. The Council has agreed to:
    • complete a Children Act statutory complaints procedure stage two investigation within 65 working days of the date of this final decision and notify Mr X of his rights under the procedure.

Back to top

Final decision

  1. We have upheld this complaint because the Council has agreed to resolve the complaint early by providing a proportionate remedy for the injustice caused to Mr X.

Back to top

Investigator's decision on behalf of the Ombudsman

Print this page

LGO logogram

Review your privacy settings

Required cookies

These cookies enable the website to function properly. You can only disable these by changing your browser preferences, but this will affect how the website performs.

View required cookies

Analytical cookies

Google Analytics cookies help us improve the performance of the website by understanding how visitors use the site.
We recommend you set these 'ON'.

View analytical cookies

In using Google Analytics, we do not collect or store personal information that could identify you (for example your name or address). We do not allow Google to use or share our analytics data. Google has developed a tool to help you opt out of Google Analytics cookies.

Privacy settings